I-65 Safety and Efficiency is an Indiana Department of Transportation (INDOT) project to improve traffic flow and safety along I-65 on the southeast side of Indianapolis. Construction began in spring 2025 and is expected to last about two years. 

Curb Repairs Scheduled at Keystone Avenue

  • Right turn onto northbound Keystone Avenue from the northbound I-65 exit ramp closed Monday, July 20 (7 a.m. to 5 p.m.)
  • Left turn onto northbound Keystone Avenue from the southbound I-65 exit ramp closed Monday, July 20 through Thursday, July 23 (7 a.m. Monday to 5 p.m. Thursday)

 

I-65 Bridge Painting Scheduled over Pleasant Run Parkways

  • Westbound Pleasant Run Parkway North closed between Olive and Shelby streets Monday, July 20 through Wednesday, July 22 (7 a.m. Monday to noon Wednesday)
  • Eastbound Pleasant Run Parkway South closed between Shelby and Olive streets Wednesday, July 22 through Friday, July 24 (Noon Wednesday to 5 p.m. Friday)

Click the maps to expand, download and share.

Timeline

Sign Up For Updates

Follow the progress of I-65 Safety and Efficiency and receive project updates by email and text.

Email Updates

Sign up for I-65 Safety & Efficiency email updates to get the latest news about the project delivered to your inbox.

Text Updates

Sign up for I-65 Safety & Efficiency text updates to receive the latest news, information and more about the project.

I-65/I-70 Pavement Replacement

Status: Under construction

  • Pavement is being replaced from just north of Fletcher Avenue to just south of Washington Street.
  • The closed ramp between Virginia Avenue and Calvary Street is being removed.
  • The storm sewer system is being replaced.

Abandoned Railroad Bridge Removal

Status: COMPLETE

  • Crews removed the abandoned railroad bridge north of Fletcher Avenue over I-65/I-70 in spring 2026.

I-65/I-70 Interchange 

  • Several ramps at the I-65/I-70 interchange will be limited to one travel lane to accommodate I-65 construction
  • Lane closures will remain in place through the end of 2025

Northbound I-65 bridge over Morris and Prospect Streets

Status: Complete

  • The bridge was rehabilitated with a new deck and beams.
  • The left side was completed in 2025, and the right side in 2026.

Ramp from northbound I-65 to Morris and Prospect Streets

Status: Complete

  • Crews reconstructed the ramp in spring 2026.

Morris Street bridge and Prospect Street bridge over I-65

Status: Work is expected to begin in late summer 2026.

  • The Morris Street bridge and the Prospect Street bridge over I-65 will be rehabilitated to accommodate 10-foot sidewalks on both sides.
  • Both bridges will need to close one at a time for about two weeks to complete the work.

Morris/Prospect Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • All sidewalks at Morris/Prospect will be replaced.
  • ADA ramps will be updated as needed.
  • Underpass lighting will also be updated.

Shelby Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

 

  • Sidewalks were recently updated at this location.
  • Underpass lighting will be updated to improve safety and visibility.

Naomi Street and Pleasant Run Bridges

Status: Under construction

  • Northbound I-65 bridges are being widened to add a fourth travel lane.
  • Crews added capacity using the inside shoulder in 2025 and are working on the outside shoulders in 2026.

Pleasant Run Trail

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • A portion of Pleasant Run Trail will be replaced when the Pleasant Run overpass is widened.
  • Underpass lighting will be updated.

Naomi Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • The sidewalk and curb under the Naomi Street underpass will be replaced.
  • Inconsistent slopes under the underpass will be leveled.
  • Underpass lighting will also be updated.

Raymond Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • All sidewalks within INDOT right-of-way are being replaced.
  • ADA ramps will be updated as needed.

Raymond Street Ramps

Status: Closed for reconstruction; Expected to open early Fall 2026, weather permitting

  • Crews are reconstructing the ramps and paving new asphalt pavement
  • The following ramps are closed: 
    • Ramp from southbound I-65 to Raymond Street
    • Ramps from Raymond Street to southbound I-65
    • Ramp from eastbound Raymond Street to northbound I-65 
  • The following ramps are expected to close on or after Friday, July 24:
    • Ramp from northbound I-65 to eastbound and westbound Raymond Street
    • Ramp from westbound Raymond Street to northbound I-65

Added Capacity: Inside

Status: COMPLETE

  • Crews added capacity using the inside shoulder of I-65 in 2025.
  • Traffic is now on the new pavement, so work can start on widening the outside. 
  • Most of the widening utilizes the existing inside shoulder, with the southern third of the project widening to the outside.
  • When complete, there will be four lanes in each direction on I-65 between I-70 and I-465.

Troy, Nelson, southern and Bradbury Avenue Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • Broken sidewalk panels are being replaced.
  • Underpass lighting will be updated.

Keystone Avenue Ramp

Status: COMPLETE

  • Crews reconstructed the ramp from northbound I-65 to Keystone Avenue (Exit 107) in summer 2025.

Keystone Avenue Ramp to Southbound I-65

Status: COMPLETE

  • Crews reconstructed the ramp in spring 2026.

Southbound I-65 Ramp to Keystone Avenue

Status: COMPLETE

  • Crews reconstructed the ramp in spring 2026. 

Keystone Avenue Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • All ADA curb ramps are being updated.
  • Pedestrian push buttons will be added.

Keystone Avenue Ramp to Northbound I-65

Status: Complete

  • Crews reconstructed the ramp in spring 2026.

Added Capacity: Outside

Status: Under construction

  • Crews are adding capacity to the outside lanes in 2026.
  • Widening is happening to the outside for the southern third of the project corridor.
  • Crews are adding a lane in both directions of I-65 from I-70 to I-465.
  • When complete, there will be four lanes in each direction.

Hanna Avenue Bridge Replacement

Status: COMPLETE

  • The new Hanna Avenue overpass bridge opened in fall 2025.
  • A nearly 10-foot shared use path for pedestrians was added the south side of the bridge.
  • A six-foot sidewalk was added on the north side of the bridge.