I-65 Safety and Efficiency is an Indiana Department of Transportation (INDOT) project to improve traffic flow and safety along I-65 on the southeast side of Indianapolis. Construction began in spring 2025 and is expected to last about two years. Two lanes of I-65 will remain open in each direction the majority of the time during construction.

Changing traffic pattern near I-65/I-70 North Split after weekend ramp closures: Learn More

Click the maps to expand, download and share.

Timeline

Sign Up For Updates

Follow the progress of I-65 Safety and Efficiency and receive project updates by email and text.

Email Updates

Sign up for I-65 Safety & Efficiency email updates to get the latest news about the project delivered to your inbox.

Text Updates

Sign up for I-65 Safety & Efficiency text updates to receive the latest news, information and more about the project.

I-65/I-70 Pavement Replacement

Status: Under construction

  • Pavement is being replaced from just north of Fletcher Avenue to just south of Washington Street.
  • The closed ramp between Virginia Avenue and Calvary Street will be removed and upgraded.
  • The storm sewer system is being replaced.
  • Ramp and lane restrictions will remain in place during spring/summer 2026.

Abandoned Railroad Bridge Removal

Status: In progress

  • The abandoned railroad bridge north of Fletcher Avenue over I-65/I-70 is being removed.
  • Crews will remove the foundations of the bridge over the course of three weekend closures on I-65 (CLICK TO LEARN MORE)

I-65/I-70 Interchange 

  • Several ramps at the I-65/I-70 interchange will be limited to one travel lane to accommodate I-65 construction
  • Lane closures will remain in place through the end of 2025

Northbound I-65 bridge over Morris/Prospect Street

Status: Under construction

  • The bridge is being rehabilitated with a new deck and beams.
  • The left side was completed in 2025, and crews are working on the right side in 2026.

Morris/Prospect bridge              over I-65

Status: Work is expected to begin in 2026.

  • The bridge will be rehabilitated to accommodate 10-foot sidewalks on both sides.
  • The bridge will need to close for about a month to complete the work.

Morris/Prospect Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • All sidewalks at Morris/Prospect will be replaced.
  • ADA ramps will be updated as needed.
  • Underpass lighting will also be updated.

Shelby Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

 

  • Sidewalks were recently updated at this location.
  • Underpass lighting will be updated to improve safety and visibility.

Naomi Street and Pleasant Run Bridges

Status: Under construction

Pleasant Run Parkway North Drive is closed between Olive and Linden streets for bridge construction. It’s expected to reopen Monday, April 6. Once reopened, East Pleasant Run Parkway South Drive will close in the same area for a few weeks for I-65 bridge widening work.

Northbound I-65 bridges are being widened to add a fourth travel lane.

  • Crews added capacity using the inside shoulder in 2025 and are working on the outside shoulders in 2026.

Pleasant Run Trail

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • A portion of Pleasant Run Trail will be replaced when the Pleasant Run overpass is widened.
  • Underpass lighting will be updated.

Naomi Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • The sidewalk and curb under the Naomi Street underpass will be replaced.
  • Inconsistent slopes under the underpass will be leveled.
  • Underpass lighting will also be updated.

Raymond Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • All sidewalks within INDOT right-of-way are being replaced.
  • ADA ramps will be updated as needed.

Added Capacity: Inside

Status: COMPLETE

  • Crews added capacity using the inside shoulder of I-65 in 2025.
  • Traffic is now on the new pavement, so work can start on widening the outside. 
  • Most of the widening utilizes the existing inside shoulder, with the southern third of the project widening to the outside.
  • When complete, there will be four lanes in each direction on I-65 between I-70 and I-465.

Troy, Nelson, southern and Bradbury Avenue Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • Broken sidewalk panels are being replaced.
  • Underpass lighting will be updated.

Keystone Avenue Ramp

Status: COMPLETE

  • Crews reconstructed the ramp from northbound I-65 to Keystone Avenue (Exit 107) in summer 2025.

Keystone Avenue Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • All ADA curb ramps are being updated.
  • Pedestrian push buttons will be added.

Keystone Avenue Ramp to Southbound I-65

Status: Closed

  • Crews are removing current asphalt and replacing it with new material
  • Improved ramp is expected to reopen in late June, weather permitting 

Southbound I-65 Ramp to Keystone Avenue

Status: Closed

  • Crews are removing current asphalt and replacing it with new material
  • Improved ramp is expected to reopen in late June, weather permitting 

Added Capacity: Outside

Status: Under construction

  • Crews are adding capacity to the outside lanes in 2026.
  • Widening is happening to the outside for the southern third of the project corridor.
  • Crews are adding a lane in both directions of I-65 from I-70 to I-465.
  • When complete, there will be four lanes in each direction.

Hanna Avenue Bridge Replacement

Status: COMPLETE

  • The new Hanna Avenue overpass bridge opened in fall 2025.
  • A nearly 10-foot shared use path for pedestrians was added the south side of the bridge.
  • A six-foot sidewalk was added on the north side of the bridge.

I-65/I-465 Interchange 

  • The ramp from southbound I-65 to eastbound I-465 will be limited to one travel lane to accommodate I-65 construction
  • Lane closures will remain in place through the end of 2025