At least two lanes of I-65 between I-465 and I-70 will remain open in each direction, a majority of the time.

.

Some ramps at the I-65/I-70 and I-465 interchanges will be reduced to one lane in 2025.

Click the maps to expand, download and share.

Timeline

Sign Up For Updates

Follow the progress of I-65 Safety and Efficiency and receive project updates by email and text.

Email Updates

Sign up for I-65 Safety & Efficiency email updates to get the latest news about the project delivered to your inbox.

Text Updates

Sign up for I-65 Safety & Efficiency text updates to receive the latest news, information and more about the project.

I-65/I-70 Pavement Replacement

Status: Work is expected to begin in 2026.

  • Pavement is being replaced from just north of the Fletcher Avenue overpass to just south of the I-65/I-70 overpass.
  • The closed ramp between Virginia Avenue and Calvary Street will be removed and upgraded.
  • The storm sewer system is being replaced.

Abandoned Railroad Bridge Removal

Status: Work is expected to begin in 2026.

  • The abandoned railroad bridge north of Fletcher Avenue over I-65/I-70 is being removed.

I-65/I-70 Interchange 

  • Several ramps at the I-65/I-70 interchange will be limited to one travel lane to accommodate I-65 construction
  • Lane closures will remain in place through the end of 2025

Northbound I-65 bridge over Morris/Prospect Street

Status: Under construction

  • The bridge will be rehabilitated.
  • A new deck will be installed.
  • New beams will be installed. 

Morris/Prospect bridge              over I-65

Status: Work is expected to begin in 2026.

  • The bridge will be rehabilitated to accommodate 10-foot sidewalks on both sides.
  • The bridge will need to close for about a month to complete the work.

Morris/Prospect Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • All sidewalks at Morris/Prospect will be replaced.
  • ADA ramps will be updated as needed.
  • Underpass lighting will also be updated.

Shelby Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

 

  • Sidewalks were recently updated at this location.
  • Underpass lighting will be updated to improve safety and visibility.

Naomi Street and Pleasant Run Bridges

Status: Under construction

  • Northbound I-65 bridges are being widened to add a fourth travel lane.
  • In 2025, construction will focus on adding capacity using the inside shoulder.
  • In 2026, crews will widen the outer lanes.

Pleasant Run Trail

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • A portion of Pleasant Run Trail will be replaced when the Pleasant Run overpass is widened.
  • Underpass lighting will be updated.

Naomi Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • The sidewalk and curb under the Naomi Street underpass will be replaced.
  • Inconsistent slopes under the underpass will be leveled.
  • Underpass lighting will also be updated.

Raymond Street Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • All sidewalks within INDOT right-of-way are being replaced.
  • ADA ramps will be updated as needed.

Added Capacity: Inside

Status: Under construction, single lane closure in both directions

  • Crews are adding capacity utilizing the inside shoulder in 2025.
  • Crews are adding a lane in both directions of I-65 from I-465 to I-70.
  • When complete, there will be four lanes in each direction.
  • Most of the widening utilizes the existing inside shoulder, with the southern third of the project widening to the outside.

Troy, Nelson, southern and Bradbury Avenue Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • Broken sidewalk panels are being replaced.
  • Underpass lighting will be updated.

Added Capacity: Outside

Status: Work is expected to begin in 2026.

  • Crews will begin adding capacity to the outside lanes in 2026.
  • Widening is happening to the outside for the southern third of the project corridor.
  • Crews are adding a lane in both directions of I-65 from I-465 to I-70.
  • When complete, there will be four lanes in each direction.

Keystone Avenue Ramp

Status: COMPLETE

  • Crews reconstructed the ramp from northbound I-65 to Keystone Avenue (Exit 107) in summer 2025.

Keystone Avenue Sidewalks

Status: Most sidewalk improvements are expected to begin in 2027 as work wraps up on the project.

  • All ADA curb ramps are being updated.
  • Pedestrian push buttons will be added.

Hanna Avenue Bridge Replacement

Status: Closed for replacement

  • The Hanna Avenue overpass bridge is being replaced with a new bridge.
  • It’s expected to reopen late this fall.
  • A nearly 10-foot shared use path for pedestrians will be added on the south side of the bridge.
  • A six-foot sidewalk will be added on the north side of the bridge.

I-65/I-465 Interchange 

  • The ramp from southbound I-65 to eastbound I-465 will be limited to one travel lane to accommodate I-65 construction
  • Lane closures will remain in place through the end of 2025

NORTHBOUND I-65 CLOSURES SCHEDULED THIS WEEKEND

9 p.m. Friday, August 15 through 6 a.m. Monday, August 18

The closures extend from the I-65/I-465 interchange to the I-65/I-70 interchange and include the following northbound I-65 ramps:

  • Eastbound I-465 to northbound I-65
  • Westbound I-465 to northbound I-65
  • Keystone Avenue entrance/exit ramps
  • Raymond Street entrance/exit ramps
  • Morris/Prospect exit ramp