Two Raymond Street ramps at northbound I-65 are expected to temporarily close later this month. Both will be improved and reconstructed with new asphalt pavement.
- Ramp from northbound I-65 to eastbound and westbound Raymond Street
- Ramp from westbound Raymond Street to northbound I-65
The ramps are expected to close around 6 a.m. on or after Friday, July 24. They are expected to reopen by October, weather permitting.
Traffic Shift on I-65/I-70 Pavement Replacement
Traffic is expected to shift to new roadway next week as I-65/I-70 pavement improvements continue between Fletcher Avenue and Washington Street.
Following the shift, northbound I-65 traffic will be separated from the work zone by barrier wall. Drivers continuing on northbound I-65 will keep left, and drivers exiting at Washington Street will need to keep right before Fletcher Avenue.
Overnight lane and ramp restrictions are expected while crews complete the traffic shift. Details will be shared next week.
Actual dates and anticipated work may be adjusted if inclement weather or other unforeseen circumstances occur.
Construction Speed Limit
The construction zone speed limit remains active on I-65. A reduced speed of 45 mph is in place for the duration of I-65 Safety and Efficiency work. It is important for drivers to slow down and avoid distractions in work zones.
Find more information at I65SafetyandEfficiency.com and follow the project on Facebook and X.